The Nevada Department of Transportation has substantially completed a two-year project to repave and enhance U.S. 50 between Spooner Summit and the Nevada/California border at Stateline.
Drivers will only see brief roadway finishing work as minor elements of construction complete over coming weeks.
Since launching in April 2025, the project resurfaced just over 13 miles of U.S. 50 from the Nevada/California border at Stateline to the Spooner Summit Trailhead near the U.S. 50/State Route 28 intersection, providing a smoother, safer drive for the approximately 26,000 drivers who travel the busy stretch of highway daily.
Project improvements
The following improvements were made:
Repaved just over 13 miles of U.S. 50, an equivalent of 55 individual lane miles.
Between Spooner Summit and Glenbrook, centerline striping was expanded to two sets of double yellow lines with a four-foot separation between traffic directions to reduce potential head-on crashes and enhance safety.
To also help reduce cross-over crashes, centerline rumble strips were enhanced between Round Hill Pines and Glenbrook.
Installed 13 miles, or 228,000 linear feet, of Intelligent Traffic Systems (ITS) underground conduit line to further connect and power roadway cameras, road/weather information systems, traffic counters, traffic flow detectors, automated chain/snow tire control signage, and more.
More than 2,000 feet of existing culvert pipes were reinforced, 52 new storm drain inlets, 1,300 feet of new storm sewer culvert pipe, and approximately 38,000 feet of new roadside curb and gutter installed, helping protect Lake Tahoe clarity by channeling stormwater into designated drainage systems.
Upgraded guardrail and concrete barrier rail to enhance safety.